Hello,
I couldn't find any information about this behavior, so I ask here:
Add a geo sop node, dive inside
Delete the file sop
Add a tube sop.
Add bound sop after the tube
Turn the viewport selection to points (2), wire display, select transform tool and select all points.
==> Iif your bound sop has a odd amount (not divisible by 2) of divisions on Z axis, the pivot will be wierd
if it has even amount (divisible by 2) of divisions on Z axis, pivot will be correct.
Any explaination for this behavior please?
Thanks
Bound SOP pivot problem
1599 1 0- Rodolphe Coudeyre
- Member
- 3 posts
- Joined: Sept. 2014
- Offline
- Rodolphe Coudeyre
- Member
- 3 posts
- Joined: Sept. 2014
- Offline
-
- Quick Links